Related Questions
What is the correct answer?
4
Which one of the following is not an excavating and moving type of equipment?
What is the correct answer?
4
The Overall in-charge of an organisation at the site responsible for the execution of the works, is
What is the correct answer?
4
Interfering float is the difference between
A. Total float and free float
B. Total float and independent float
C. Free float and independent float
What is the correct answer?
4
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
What is the correct answer?
4
The process of incorporating changes and rescheduling or replanning is called
D. Critical path scheduling
What is the correct answer?
4
A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
What is the correct answer?
4
The time which results in the leasi, possible construction cost of an activity, is known as
What is the correct answer?
4
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
What is the correct answer?
4
The constraints in case of resource smoothening operation would be
C. Both resources and project duration time
What is the correct answer?
4
Which one of the following represents an activity?
A. Excavation for foundation
C. Setting of question paper
What is the correct answer?
4
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
What is the correct answer?
4
In PERT analysis, the time estimates of activities and probability of their occurrence follow
A. Normal distribution curve
B. Poisson's distribution curve
C. Beta distribution curve
What is the correct answer?
4
The critical activity has
What is the correct answer?
4
Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements
A. 1, 3 and 4 are correct
B. 2, 3 and 4 are correct
C. 1, 2 and 3 are correct
D. 1, 2 and 4 are correct
What is the correct answer?
4
Free float for any activity is defined as the difference between
A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successor activity
What is the correct answer?
4
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
What is the correct answer?
4
The most suitable type of equipment for compaction of cohesive soils is
A. Smooth-wheeled rollers
What is the correct answer?
4
Select the incorrect statement.
A. A critical path always begins at the very first event.
B. A critical path always terminates at the last event.
C. Critical activities control the project duration.
D. Critical activity is the one for which free float is zero.
What is the correct answer?
4
For completion of a project, the critical path of the network represents
What is the correct answer?
4
During the construction period, price variation clause in contracts caters to
A. Increase in rates of only important materials
B. Variation in cost in materials element, labour element and petrol-oillubricant element
C. Variation in total cost of the project on an ad hoc basis
What is the correct answer?
4
Which of the following is a weakness of bar chart?
A. Interdependencies of activities
What is the correct answer?
4
PERT is
A. An analytic in concept
B. Limited of event oriented diagrams
C. Used for research and development projects
What is the correct answer?
4
A critical ratio scheduling
A. Determines the status of each activity
B. Adjusts automatically changes in activity progress
What is the correct answer?
4
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
What is the correct answer?
4
Frederick W. Taylor introduced a system of working known as
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
What is the correct answer?
4
Military organisation is known as
B. Line and staff organisation
C. Functional organisation
What is the correct answer?
4
Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
What is the correct answer?
4
Sinking fund is
A. The fund for rebuilding a structure when its economic life is over
B. Raised to meet maintenance costs
C. The total sum to be paid to the municipal authorities by the tenants
D. A part of the money kept in reserve for providing additional structures and structural modifications
What is the correct answer?
4
Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements
A. 1, 2 and 3 are correct
C. 2, 3 and 4 are correct
D. 1, 2 and 4 are correct
What is the correct answer?
4
PERT technique of network analysis is mainly useful for
B. Large and complex projects
C. Research and development projects
D. Deterministic activities