Home
Current Affairs January 2024

What is the correct answer?

4

The difference between the time avail-to do a job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

Correct Answer :

B. Float


Related Questions

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

Select the incorrect statement.

A. A critical path always begins at the very first event.

B. A critical path always terminates at the last event.

C. Critical activities control the project duration.

D. Critical activity is the one for which free float is zero.

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

Power stations are generally treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. Electrical construction

What is the correct answer?

4

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

A. 8 days

B. 9 days

C. 10 days

D. 15 days

What is the correct answer?

4

For completion of a project, the critical path of the network represents

A. Minimum time

B. Maximum time

C. Maximum cost

D. Minimum cost

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

Which of the following earth moving machines has the shortest cycle time?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

Which one of the following represents an activity?

A. Excavation for foundation

B. Curing of concrete

C. Setting of question paper

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. An activity of a project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn to scale from left to right

What is the correct answer?

4

Which one of the following represents an event?

A. Concrete cured

B. Fixing of door

C. Plastering of walls

D. Selecting sites

What is the correct answer?

4

Residential buildings are treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. Private construction

What is the correct answer?

4

The time which results in the leasi, possible construction cost of an activity, is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time

B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time

C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

D. All the above

What is the correct answer?

4

A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

A. 20 kg/tonne

B. 30 kg/tonne

C. 40 kg/tonne

D. 50 kg/tonne

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

Critical path method

A. Is an improvement upon bar chart method

B. Provides a realistic approach to daily problems

C. Avoids delays which are very common in bar charts

D. All the above

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

An event is indicated on the network by a number enclosed in

A. A circle

B. A square

C. A triangle

D. All the above

What is the correct answer?

4

Crash project duration is obtained by summing the

A. Normal durations for all the activities

B. Crash durations for all activities

C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

For the execution of a project, a contractor is

A. A person

B. A firm

C. An agency

D. All the above

What is the correct answer?

4

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

A. EF = ES + D

B. LS = LF - D

C. LF = LS + D

D. All the above

What is the correct answer?

4

Which of the following is not a PERT event?

A. Site investigation started

B. Sessional work completed

C. Bus starts from Jaipur

D. Class is being attended

What is the correct answer?

4

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

A. 4 days

B. 6 days

C. 10 days

D. 16 days

What is the correct answer?

4

Select the incorrect statement.

A. Earliest start of an activity is the early event time of the node it leaves.

B. Latest finish of an activity is the late event time of the node it enters.

C. Latest start of an activity is its latest finish minus its duration.

D. None of the above

What is the correct answer?

4

Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4

B. 3, 1, 4, 2

C. 3, 1, 2, 4

D. 1, 3, 4, 2

What is the correct answer?

4

A construction schedule is prepared after collecting

A. Number of operations

B. Output of labour

C. Output of machinery

D. All the above

What is the correct answer?

4

Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.

A. A is correct but R is not correct

B. R is correct but A is not correct

C. Both A and R is correct

D. Both A and R is incorrect