Event
Float
Duration
Constraint
B. Float
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
A critical path always begins at the very first event.
A critical path always terminates at the last event.
Critical activities control the project duration.
Critical activity is the one for which free float is zero.
An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
Light construction
Heavy construction
Industrial construction
Electrical construction
8 days
9 days
10 days
15 days
Minimum time
Maximum time
Maximum cost
Minimum cost
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
All the above
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Drag line
Hoe
Clam shell
Dipper shovel
Excavation for foundation
Curing of concrete
Setting of question paper
All the above
An activity of a project is denoted by an arrow on the net work
The tail of the arrow indicates the start of the activity
The head of the arrow indicates the end of the activity
The arrows are drawn to scale from left to right
Concrete cured
Fixing of door
Plastering of walls
Selecting sites
Light construction
Heavy construction
Industrial construction
Private construction
Normal time
Slow time
Crash time
Standard time
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above
20 kg/tonne
30 kg/tonne
40 kg/tonne
50 kg/tonne
1910
1920
1930
1940
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above
Minor works
Major works
Large projects
All the Above
A circle
A square
A triangle
All the above
Normal durations for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
A person
A firm
An agency
All the above
EF = ES + D
LS = LF - D
LF = LS + D
All the above
Site investigation started
Sessional work completed
Bus starts from Jaipur
Class is being attended
4 days
6 days
10 days
16 days
Earliest start of an activity is the early event time of the node it leaves.
Latest finish of an activity is the late event time of the node it enters.
Latest start of an activity is its latest finish minus its duration.
None of the above
1, 3, 2, 4
3, 1, 4, 2
3, 1, 2, 4
1, 3, 4, 2
Number of operations
Output of labour
Output of machinery
All the above
A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect