Home
Current Affairs January 2024

What is the correct answer?

4

Job evaluation is the method of determining the

A. Relative worth of jobs

B. Skills required by a worker

C. Contribution of a worker

D. Contribution of a job

Correct Answer :

A. Relative worth of jobs


Related Questions

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Process layout is employed for

A. Batch production

B. Continuous type of product

C. Effective utilisation of machines

D. All of the above

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

What is the correct answer?

4

In process layout

A. Handling and backtracking of materials is too much

B. Production control is more difficult and costly

C. Routing and scheduling is more difficult

D. All of the above

What is the correct answer?

4

Work sampling is applied for

A. Estimation of the percentage utilisation of machine tools

B. Estimating the percentage of the time consumed by various job activities

C. Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible

D. All of the above

What is the correct answer?

4

In A-B-C analysis, which class of items are generally large in number?

A. A

B. B

C. C

D. None of these

What is the correct answer?

4

According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse minimum DAM = Defender's Adverse minimum)

A. CAM < DAM

B. CAM > DAM

C. CAM = DAM

D. There is no such criterion

What is the correct answer?

4

Product layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

M.T.M. is used to

A. Improve existing methods

B. Establish time standards

C. Develop effective methods in advance of the beginning of production

D. All of the above

What is the correct answer?

4

The most important function of inventory control is

A. Stock control system

B. To run the stores effectively

C. Technical responsibility for the state of materials

D. All of the above

What is the correct answer?

4

The main objective of work measurement is to

A. Plan and schedule of production

B. Formulate a proper incentive scheme

C. Estimate the selling prices and delivery dates

D. All of the above

What is the correct answer?

4

Time study is carried out

A. By finding all the significant informations regarding the job, work place and machine tool etc.

B. By breaking up each operation into small elements which are measurable with the help of the measuring device accurately

C. By observing and recording the time taken by the operator for an operation

D. All of the above

What is the correct answer?

4

The value engineering technique in which experts of the same rank assemble for product development is called

A. Delphi

B. Brain storming

C. Morphological analysis

D. Direct expert comparison

What is the correct answer?

4

When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

What is the correct answer?

4

The most suitable incentive plan for the maintenance section of an industry will be

A. Piece rate system

B. Group incentive plan

C. Profit sharing plans

D. Simplification

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

A systematic job improvement sequence will consist of

A. Motion study

B. Time study

C. Job enrichment

D. All of these

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Scanlon Plan

B. Rowan Plan

C. Taylor Differential Piece Rate System

D. Halsey Premium Plan

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

Pick up the incorrect statement from the following

A. An activity of the project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn (to scale from) left to right

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

Product layout is employed for

A. Batch production

B. Continuous production

C. Effective utilization of machine

D. All of the above

What is the correct answer?

4

ABC analysis deals with

A. Analysis of process chart

B. Flow of material

C. Ordering schedule of job

D. Controlling inventory costs money

What is the correct answer?

4

CPM has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

What is the correct answer?

4

Direct expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. None of these

What is the correct answer?

4

Pick up the correct step used for scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Sequence of various activities is made according to their importance

D. All of the above

What is the correct answer?

4

Queueing theory is used for

A. Inventory problems

B. Traffic congestion studies

C. Job-shop scheduling

D. All of the above