Home

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

Related Questions

  1. The average time recorded by work study man for an operation is called
  2. PERT analysis is based upon
  3. The start or completion of task is called
  4. In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
  5. The most suitable incentive plan for the maintenance section of an industry will be
  6. Time study is carried out to determine the time required to complete job by
  7. PERT is the
  8. A-B-C analysis is used in
  9. In a PERT chart
  10. One of the basic essentials of an incentive plan is that
  11. F. W. Taylor introduced a system of organisation known as
  12. At the breakeven point,
  13. Under the Apprenticeship Act
  14. Breakeven point is the point where
  15. The basic difference between PERT and CPM is that
  16. The routing function in a production system design is concerned with
  17. The value engineering technique in which experts of the same rank assemble for product development is…
  18. The correct sequence of phases in value engineering is
  19. Pick up the correct statement from the following
  20. Routing
  21. In Halsey 50-50 plan, output standards are established
  22. Which of the following statement is correct?
  23. In A-B-C analysis, which class of items are generally large in number?
  24. The artificial activity, which indicates that an activity following it cannot be started unless, the…
  25. Standard time is equal to
  26. Which of the following layouts is suited to job production?
  27. Graphical method, simplex method, and transportation method are concerned with
  28. In steel plant the most important system for materials handling is
  29. Which of the following conditions are necessary for applying linear programming?
  30. Which of the following plans motivates supervisors by paying a premium on time saved by workers?

Please do not use chat terms. Example: avoid using "grt" instead of "great".