Home
Current Affairs January 2024

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

Correct Answer :

C. 0.84


Related Questions

What is the correct answer?

4

The linear programming techniques can be applied successfully to industries like

A. Iron and steel

B. Food processing

C. Oil and chemical

D. All of the above

What is the correct answer?

4

For material transportation, conveyors are used when the prevailing conditions include

A. Loads are uniform

B. Routes do not vary

C. Materials move relatively continuously

D. All of these

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

Dispatching

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with the starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Queuing theory is associated with

A. Sales

B. Inspection time

C. Waiting time

D. Production time

What is the correct answer?

4

Product layout is employed for

A. Batch production

B. Continuous production

C. Effective utilization of machine

D. All of the above

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

What is the correct answer?

4

PERT has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

Which of the following are the principles of material handling?

A. Keep all the handling to the minimum

B. Select only efficient handling equipment

C. Move the heaviest weight to the least distance

D. All of the above

What is the correct answer?

4

The simplex method is the basic method for

A. Value analysis

B. Operation research

C. Linear programming

D. Model analysis

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Standing orders which are statutory are applicable to

A. All industries

B. All process industries and thermal power plants

C. Only major industries

D. All industries employing more than 100 workers

What is the correct answer?

4

CPM stands for

A. Combined Process Method

B. Critical Path Method

C. Common Planning Method

D. Critical Process Method

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by

A. AP/C

B. 2AP/C

C. √(AP/C)

D. (AP/C)2

What is the correct answer?

4

Current assets include

A. Manufacturing plant

B. Manufacturing plant and equipment

C. Inventories

D. Common stock held by the firm

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

A systematic job improvement sequence will consist of

A. Motion study

B. Time study

C. Job enrichment

D. All of these

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from noncritical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All of the above

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

What is the correct answer?

4

The difference between the time available to do the job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

A. A standard rating system

B. A merit rating system

C. A job evaluation system

D. His individual performance

What is the correct answer?

4

Fixed position layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

In steel plant the most important system for materials handling is

A. Conveyors

B. Cranes and hoists

C. Trucks

D. Locos

What is the correct answer?

4

Standard time is equal to

A. (Normal time) - (allowances)

B. (Normal time) + (allowances)

C. Representative time multiplied by rating factor

D. Normal time taken by an operation

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production