Home
Current Affairs January 2024

What is the correct answer?

4

The chart which gives an estimate about the amount of materials handling between various work stations is known as

A. Flow chart

B. Process chart

C. Travel chart

D. Operation chart

Correct Answer :

C. Travel chart


Related Questions

What is the correct answer?

4

At the breakeven point,

A. Total cost is more than the sales revenue

B. Total cost is less than the sales revenue

C. Total cost is equal to sales revenue

D. Fixed cost is equal to variable cost

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches

A. 50 %

B. 66.67 %

C. 75 %

D. 80 %

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

A diagram showing the path followed by men and materials while performing a task is known as

A. String diagram

B. Flow process chart

C. Travel chart

D. Flow diagram

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

Pick up the correct statement from the following

A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed

B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project

D. All of the above

What is the correct answer?

4

Line organisation is suitable for

A. Sugar industries

B. Oil refining industries

C. Spinning and weaving industries

D. All of these

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

Dispatching

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with the starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Under the Apprenticeship Act

A. All industries have to necessarily train the apprentices

B. Industries have to train apprentices according to their requirement

C. All industries employing more than 100 workers have to recruit apprentices

D. Only industries employing more than 500 workers have to recruit apprentices

What is the correct answer?

4

The most suitable incentive plan for the maintenance section of an industry will be

A. Piece rate system

B. Group incentive plan

C. Profit sharing plans

D. Simplification

What is the correct answer?

4

The process capability of a machine is defined as the capability of the machine to

A. Produces a definite volume of work per minute

B. Perform definite number of operations

C. Produce job at a definite spectrum of speed

D. Holds a definite spectrum of tolerance and surface finish

What is the correct answer?

4

Templates are used for

A. A planning layout

B. Flow of material

C. Advancing a programme in automatic machines

D. Copying complicated profiles

What is the correct answer?

4

Pick up the correct statement from the following

A. Programmer evaluation and review technique is event oriented

B. Programmer evaluation and review technique is not event oriented

C. Critical path method is event oriented

D. None of the above

What is the correct answer?

4

Linear programming can be applied successfully to

A. Chemical industry

B. Oil industry

C. Banks

D. All of these

What is the correct answer?

4

Bin card is used in

A. Administrative wing

B. Workshop

C. Foundry shop

D. Stores

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

Emergency rush order can be pushed more effectively in

A. Job production

B. Automatic production

C. Continuous production

D. Intermittent production

What is the correct answer?

4

An event is indicated on the network by

A. A straight line

B. A number enclosed in a circle or a square

C. A straight line with circles at the ends

D. A dotted line

What is the correct answer?

4

In manufacturing management, the term 'Dispatching' is used to describe

A. Dispatch of sales order

B. Dispatch of factory mail

C. Dispatch of finished product of the user

D. Dispatch of work orders through shop floor

What is the correct answer?

4

Which of the following are the guidelines for the construction of a network diagram?

A. Each activity is represented by one and only one arrow in the network

B. Dangling must be avoided in a network diagram

C. Dummy activity consumes no time or resource

D. All of the above

What is the correct answer?

4

The simplex method is the basic method for

A. Value analysis

B. Operation research

C. Linear programming

D. Model analysis

What is the correct answer?

4

In process layout

A. Handling and backtracking of materials is too much

B. Production control is more difficult and costly

C. Routing and scheduling is more difficult

D. All of the above

What is the correct answer?

4

Time study is carried out to determine the time required to complete job by

A. A slow worker

B. A fast worker

C. An average worker

D. An apprentice

What is the correct answer?

4

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above

What is the correct answer?

4

Bar chart is suitable for

A. Large project

B. Major work

C. Minor work

D. All of these