Home
Current Affairs January 2024

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

Correct Answer :

B. 50


Related Questions

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

The start or completion of task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

In jobbing production

A. Highly skilled workers are needed

B. Unit costs are high

C. Operations are labour-intensive

D. All of these

What is the correct answer?

4

The term 'value' in value engineering refers to

A. Total cost of the product

B. Selling price of the product

C. Utility of the product

D. Manufactured cost of the product

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

The average time recorded by work study man for an operation is called

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event

What is the correct answer?

4

Gantt charts provide information about

A. Breakeven point analysis

B. Production schedule

C. Material handling layout

D. Determining selling price

What is the correct answer?

4

Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

Which of the following statement is wrong?

A. An activity consumes time and resources whereas an event does not consume time or resources.

B. The performance of a specific task is called an activity.

C. An event is an instantaneous point in time at which an activity begins or ends.

D. The turning of a job on lathe is an event whereas job turned is an activity.

What is the correct answer?

4

Pick up the correct step used for scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Sequence of various activities is made according to their importance

D. All of the above

What is the correct answer?

4

Product layout is used for

A. Job production

B. Batch production

C. Mass production

D. Any one of these

What is the correct answer?

4

In a line organisation

A. Responsibility of each individual is fixed

B. Discipline is strong

C. Quick decisions are taken

D. All of these

What is the correct answer?

4

Under the Apprenticeship Act

A. All industries have to necessarily train the apprentices

B. Industries have to train apprentices according to their requirement

C. All industries employing more than 100 workers have to recruit apprentices

D. Only industries employing more than 500 workers have to recruit apprentices

What is the correct answer?

4

The determination of standard time in a complex job system is best done through

A. Stop watch time study

B. Analysis of micro-motions

C. Grouping timing technique

D. Analysis of standard data system

What is the correct answer?

4

If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be

A. 2 HA

B. 1.33 HA

C. 1.5 HA

D. 1.15 HA

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?

A. Halsey plan

B. Gantt plan

C. Rowan plan

D. Emerson's efficiency plan

What is the correct answer?

4

Standard time is equal to

A. (Normal time) - (allowances)

B. (Normal time) + (allowances)

C. Representative time multiplied by rating factor

D. Normal time taken by an operation

What is the correct answer?

4

The objective of time study is to determine the time required to complete a job by

A. Fast worker

B. Average worker

C. Slow worker

D. New entrant

What is the correct answer?

4

Valve analysis is particularly of interest when

A. Jobbing work economics are involved

B. Production is on large scale

C. Only few components are involved

D. Costly equipment is used

What is the correct answer?

4

Actual performance of a task is called

A. An event

B. An activity

C. A duration

D. None of these