Home
Current Affairs January 2024

What is the correct answer?

4

The important file in making a PERT is

A. An event can't be accomplished until activities leading to it are completed

B. No activity from any event can be started from preceding event till it is completed

C. Length of arrow has nothing to do with time

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

Pick up the correct step used for scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Sequence of various activities is made according to their importance

D. All of the above

What is the correct answer?

4

Breakeven point is the point where

A. Fixed and variable cost lines intersect

B. Fixed and total cost lines intersect

C. Variable and total cost lines intersect

D. Sales revenue and total expensive lines intersect

What is the correct answer?

4

Actual performance of a task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

P.M.T.S. (Predetermined Motion Time Systems) include

A. M.T.M. (Method Time Measurement)

B. W.F.S. (Work Factor Systems)

C. B.M.T.S. (Basic Motion Time Study)

D. All of these

What is the correct answer?

4

The linear programming techniques can be applied successfully to industries like

A. Iron and steel

B. Food processing

C. Oil and chemical

D. All of the above

What is the correct answer?

4

When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

What is the correct answer?

4

A graphical device used to determine the breakeven point and profit potential under varying conditions of output and costs, is known as

A. Gantt chart

B. Flow chart

C. Breakeven chart

D. PERT chart

What is the correct answer?

4

PERT requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

Work study involves

A. Only method study

B. Only work measurement

C. Method study and work measurement

D. Only motion study

What is the correct answer?

4

Which of the following wage incentive plan is applied to all workers?

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity

What is the correct answer?

4

According to Rowan plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

The correct sequence of phases in value engineering is

A. Creative phase, information phase, investigation phase, evaluation phase

B. Information phase, creative phase, investigation phase, evaluation phase

C. Investigation phase, information phase, creative phase, evaluation phase

D. Creative phase, investigation phase, evaluation phase, information phase

What is the correct answer?

4

Material handling and plant location is analysed by

A. Gantt chart

B. Bin chart

C. Emerson chart

D. Travel chart

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All of the above

What is the correct answer?

4

Process layout is employed for

A. Batch production

B. Continuous type of product

C. Effective utilisation of machines

D. All of the above

What is the correct answer?

4

Which one of the following techniques is used for determining allowances in time study?

A. Acceptance sampling

B. Linear regression

C. Performance rating

D. Work sampling

What is the correct answer?

4

Process layout is also known as

A. Analytical-layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Templates are used for

A. A planning layout

B. Flow of material

C. Advancing a programme in automatic machines

D. Copying complicated profiles

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Travel charts provide

A. An idea of the flow of materials at various stages

B. A compact estimate of the handling which must be done between various work sections

C. The information for changes required in rearranging material handling equipment

D. An approximate estimate of the handling which must be done at a particular station

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

In PERT analysis, critical path is obtained by joining events having

A. +ve slack

B. -ve slack

C. Zero slack

D. Dummy activities

What is the correct answer?

4

Work study is mainly aimed at

A. Determining the most efficient method of performing a job

B. Establishing the minimum time of completion of a job

C. Developing the standard method and standard time of a job

D. Economising the motions involved on the part of the worker while performing a job

What is the correct answer?

4

The probability distribution of project completion in PERT follows following distribution

A. Normal

B. Binomial

C. Exponential

D. Gaussian

What is the correct answer?

4

String diagram is used

A. For checking the relative values of various layouts

B. When a group of workers are working at a place

C. Where processes require the operator to be moved from one place to another

D. All of the above