Home
Current Affairs January 2024

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

Correct Answer :

B. Determines the programme for the operations


Related Questions

What is the correct answer?

4

String diagram is used when

A. Team of workers is working at a place

B. Material handling is to be done

C. Idle time is to be reduced

D. All of the above

What is the correct answer?

4

A systematic job improvement sequence will consist of

A. Motion study

B. Time study

C. Job enrichment

D. All of these

What is the correct answer?

4

Work study is mainly aimed at

A. Determining the most efficient method of performing a job

B. Establishing the minimum time of completion of a job

C. Developing the standard method and standard time of a job

D. Economising the motions involved on the part of the worker while performing a job

What is the correct answer?

4

The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

A. Early finish

B. Early start

C. Late start

D. Late finish

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

What is the correct answer?

4

The most important function of inventory control is

A. Stock control system

B. To run the stores effectively

C. Technical responsibility for the state of materials

D. All of the above

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

In PERT analysis, critical path is obtained by joining events having

A. +ve slack

B. -ve slack

C. Zero slack

D. Dummy activities

What is the correct answer?

4

If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by

A. AP/C

B. 2AP/C

C. √(AP/C)

D. (AP/C)2

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

In manufacturing management, the term 'Dispatching' is used to describe

A. Dispatch of sales order

B. Dispatch of factory mail

C. Dispatch of finished product of the user

D. Dispatch of work orders through shop floor

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

Templates are used for

A. A planning layout

B. Flow of material

C. Advancing a programme in automatic machines

D. Copying complicated profiles

What is the correct answer?

4

Process layout is also known as

A. Analytical-layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

A. One-fourth

B. One-half

C. Equal to

D. Twice

What is the correct answer?

4

Micro-motion study is

A. Analysis of one stage of motion chart

B. Motion study, when seen on a time chart

C. Subdivision of an operation into therbligs and their analysis

D. Enlarged view of motion study

What is the correct answer?

4

Military type of organisation is known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

Work study is concerned with

A. Improving present method and finding standard time

B. Motivation of workers

C. Improving production capability

D. Improving production planning and control

What is the correct answer?

4

Merit Rating is the method of determining worth of

A. A job

B. An individual employee

C. A particular division in workshop

D. Machine

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

Critical path method

A. Helps in ascertaining time schedules

B. Makes better and detailed planning possible

C. Provides a standard method for communicating project plans schedules and to time and cost performance

D. All of the above

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

A. A standard rating system

B. A merit rating system

C. A job evaluation system

D. His individual performance

What is the correct answer?

4

F. W. Taylor introduced a system of organisation known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

The process capability of a machine is defined as the capability of the machine to

A. Produces a definite volume of work per minute

B. Perform definite number of operations

C. Produce job at a definite spectrum of speed

D. Holds a definite spectrum of tolerance and surface finish

What is the correct answer?

4

Choose the wrong statement Time study is used to

A. Determine overhead expenses

B. Provide a basis for setting piece prices or incentive wages

C. Determine standard costs

D. Determine the capability of an operator to handle the number of machines

What is the correct answer?

4

One of the basic essentials of an incentive plan is that

A. A differential piece rate system should exist

B. Minimum wages should be guaranteed

C. Provide incentive to group efficiency performance

D. All standards should be based on time studies