Home
Current Affairs January 2024

What is the correct answer?

4

Breakeven analysis is a

A. Short term analysis

B. Long term analysis

C. Average of short and long term analysis

D. Any one of these

Correct Answer :

A. Short term analysis


Related Questions

What is the correct answer?

4

Break-even analysis shows profit when

A. Sales revenue > total cost

B. Sales revenue = total cost

C. Sales revenue < total cost

D. Variable cost < fixed cost

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

The production cost per unit can be reduced by

A. Producing more with increased inputs

B. Producing more with the same inputs

C. Eliminating idle time

D. Minimising resource waste

What is the correct answer?

4

In A-B-C analysis, which class of items are generally large in number?

A. A

B. B

C. C

D. None of these

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage

What is the correct answer?

4

Critical path moves along the activities having total float of

A. Positive value

B. Negative value

C. Zero value

D. Same value

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

Which of the following are the principles of material handling?

A. Keep all the handling to the minimum

B. Select only efficient handling equipment

C. Move the heaviest weight to the least distance

D. All of the above

What is the correct answer?

4

A graphical device used to determine the breakeven point and profit potential under varying conditions of output and costs, is known as

A. Gantt chart

B. Flow chart

C. Breakeven chart

D. PERT chart

What is the correct answer?

4

Which of the following charts are used for plant layout design?

A. Operation process chart

B. Man machine chart

C. Travel chart

D. All of these

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

Inventory management consists of

A. Effective running of stores

B. State of merchandise methods of storing and maintenance etc.

C. Stock control system

D. All of the above

What is the correct answer?

4

The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of

A. Product layout

B. Process layout

C. Fixed position layout

D. A combination of line and process layout

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of any project is known as

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

Gantt charts provide information about

A. Breakeven point analysis

B. Production schedule

C. Material handling layout

D. Determining selling price

What is the correct answer?

4

In steel plant the most important system for materials handling is

A. Conveyors

B. Cranes and hoists

C. Trucks

D. Locos

What is the correct answer?

4

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart

B. Machine load chart

C. Man-machine chart

D. Gantt chart

What is the correct answer?

4

Material handling in automobile industry is done by

A. Overhead crane

B. Trolley

C. Belt conveyor

D. All of the above

What is the correct answer?

4

Product layout is best suited where

A. One type of product is produced

B. Product is standardised

C. Product is manufactured in large quantities

D. All of the above

What is the correct answer?

4

Works cost implies

A. Primary cost

B. Factory cost

C. Factory expenses

D. Primary cost + factory expenses

What is the correct answer?

4

The grouping of activities into organisational units is called

A. Corporate plans

B. Higher level management

C. Functional authority

D. Departmentation

What is the correct answer?

4

The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store

A. Inflated system

B. Primary cost method

C. Current value method

D. Fixed price method

What is the correct answer?

4

Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

What is the correct answer?

4

Work study is concerned with

A. Improving present method and finding standard time

B. Motivation of workers

C. Improving production capability

D. Improving production planning and control

What is the correct answer?

4

One of the basic essentials of an incentive plan is that

A. A differential piece rate system should exist

B. Minimum wages should be guaranteed

C. Provide incentive to group efficiency performance

D. All standards should be based on time studies

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes