Home
Current Affairs January 2024

What is the correct answer?

4

Which of the following are the principles of material handling?

A. Keep all the handling to the minimum

B. Select only efficient handling equipment

C. Move the heaviest weight to the least distance

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

The breakeven point represents

A. The most economical level of operation of any industry

B. The time when unit can run without i loss and profit

C. Time when industry will undergo loss

D. The time when company can make maximum profits

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

Product layout is used for

A. Job production

B. Batch production

C. Mass production

D. Any one of these

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

The reasons which are basically responsible for the formation of a queue should be that

A. The average service rate Hess than the average arrival rate

B. Output rate is linearly proportional to input

C. Output rate is constant and the input varies in a random manner

D. All of the above

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All of the above

What is the correct answer?

4

Material handling and plant location is analysed by

A. Gantt chart

B. Bin chart

C. Emerson chart

D. Travel chart

What is the correct answer?

4

In process layout

A. Handling and backtracking of materials is too much

B. Production control is more difficult and costly

C. Routing and scheduling is more difficult

D. All of the above

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart

B. Machine load chart

C. Man-machine chart

D. Gantt chart

What is the correct answer?

4

Military type of organisation is known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The important file in making a PERT is

A. An event can't be accomplished until activities leading to it are completed

B. No activity from any event can be started from preceding event till it is completed

C. Length of arrow has nothing to do with time

D. All of the above

What is the correct answer?

4

Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant

A. Sinking fund method

B. Straight line method

C. ABC charging method

D. Annuity charging method

What is the correct answer?

4

Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

What is the correct answer?

4

Process layout is employed for

A. Batch production

B. Continuous type of product

C. Effective utilisation of machines

D. All of the above

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from noncritical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All of the above

What is the correct answer?

4

The unit cost in case of batch production is ________ as compared to jobbing production.

A. Same

B. Low

C. High

D. None of these

What is the correct answer?

4

Linear programming can be applied successfully to

A. Chemical industry

B. Oil industry

C. Banks

D. All of these

What is the correct answer?

4

In A-B-C analysis, which class of items are generally large in number?

A. A

B. B

C. C

D. None of these

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Scanlon Plan

B. Rowan Plan

C. Taylor Differential Piece Rate System

D. Halsey Premium Plan

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

The simplex method is the basic method for

A. Value analysis

B. Operation research

C. Linear programming

D. Model analysis

What is the correct answer?

4

The main object of scientific layout is

A. To produce better quality of product

B. To utilise maximum floor area

C. To minimise production delays

D. All of these

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

What is the correct answer?

4

A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called

A. Hoist

B. Jib crane

C. Portable elevator

D. Chain conveyor

What is the correct answer?

4

A milestone chart

A. Shows the inter dependences of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of the above

What is the correct answer?

4

Which of the following equations is not in conformity with others?

A. Organisation performance × motivation = profits

B. Knowledge × skill = ability

C. Ability × motivation = performance

D. Attitude × situation = motivation

What is the correct answer?

4

For material transportation, conveyors are used when the prevailing conditions include

A. Loads are uniform

B. Routes do not vary

C. Materials move relatively continuously

D. All of these

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines