Home
Current Affairs January 2024

What is the correct answer?

4

The amount deducted from the salary of workers towards employees provident fund is

A. Credited into reserves of company

B. Deposited in nationalised bank

C. Deposited in post office

D. Deposited in the account of worker with Provident Fund Commissioner

Correct Answer :

D. Deposited in the account of worker with Provident Fund Commissioner


Related Questions

What is the correct answer?

4

Probabilistic time for completion of any activity can be found out from

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

In fixed position layout

A. Total production cost is less

B. Material movement is less

C. Capital investment is minimum

D. All of these

What is the correct answer?

4

Product layout is employed for

A. Batch production

B. Continuous production

C. Effective utilization of machine

D. All of the above

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

In the perpetual inventory control, the material is checked when it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Alarming value

What is the correct answer?

4

The process layout is best suited where

A. Specialisation exists

B. Machines are arranged according to sequence of operation

C. Few number of non-standardised units is to be produced

D. Mass production is envisaged

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches

A. 50 %

B. 66.67 %

C. 75 %

D. 80 %

What is the correct answer?

4

In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if

A. Complete details of items in, waiting line are known

B. Arrival and waiting times are known and can be grouped to form a waiting line model

C. All variables and constants are known and form a linear equation

D. The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known

What is the correct answer?

4

Which of the following type of layout is suitable for automobile manufacturing concern?

A. Product layout

B. Process layout

C. Fixed position layout

D. Combination layout

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

Process layout is employed

A. Where low volume of production is required

B. Where similar jobs are manufactured on similar machines

C. Where machines are arranged on functional basis

D. All of the above

What is the correct answer?

4

The product layout

A. Lowers overall manufacturing time

B. Requires less space for placing machines

C. Utilises machine and labour better

D. All of these

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

Halsey plan of wage incentive

A. Is not applied to all level of workers

B. Is applied to all level of workers

C. Does not guarantee minimum wage

D. Is based upon efficiency of worker

What is the correct answer?

4

In PERT analysis, critical path is obtained by joining events having

A. +ve slack

B. -ve slack

C. Zero slack

D. Dummy activities

What is the correct answer?

4

Pick up the incorrect statement from the following. A critical ratio scheduling

A. Establishes the relative priorities among various activities on a common basis

B. Determines the status of each activity

C. Adjusts automatically changes in activity progress

D. None of the above

What is the correct answer?

4

In jobbing production

A. Highly skilled workers are needed

B. Unit costs are high

C. Operations are labour-intensive

D. All of these

What is the correct answer?

4

Time study is carried out to determine the time required to complete job by

A. A slow worker

B. A fast worker

C. An average worker

D. An apprentice

What is the correct answer?

4

The routing function in a production system design is concerned with

A. Manpower utilisation

B. Quality assurance of the product

C. Machine utilisation

D. Optimising material flow through the plant

What is the correct answer?

4

A milestone chart

A. Shows the inter dependences of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of the above

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

What is the correct answer?

4

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan

B. Taylor plan

C. Halsey premium plan

D. Gilbert plan

What is the correct answer?

4

The average time recorded by work study man for an operation is called

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

Job evaluation is the method of determining the

A. Relative worth of jobs

B. Skills required by a worker

C. Contribution of a worker

D. Contribution of a job

What is the correct answer?

4

The disadvantage of product layout is

A. High initial investment for the specialized facilities

B. Skilled labour to operate machines

C. Production time is longer, requiring more goods in inventory

D. High cost of inspection

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation