Home
Current Affairs January 2024

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

Correct Answer :

C. Programme Evaluation and Review Technique


Related Questions

What is the correct answer?

4

PERT/CPM, techniques can be used for following applications

A. Once through project

B. Maintenance jobs

C. Research and development

D. All of the above

What is the correct answer?

4

The linear programming techniques can be applied successfully to industries like

A. Iron and steel

B. Food processing

C. Oil and chemical

D. All of the above

What is the correct answer?

4

The time taken by a trained worker to perform an operation, while working a steady pace, is known as

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

A-B-C analysis is used in

A. CPM

B. PERT

C. Inventory control

D. All of these

What is the correct answer?

4

Break-even analysis can be used for

A. Short run analysis

B. Long run analysis

C. Average of above two run analysis

D. There is no such criterion

What is the correct answer?

4

Standard time as compared to normal time is

A. Greater

B. Smaller

C. Equal

D. There is no such correlation

What is the correct answer?

4

The amount deducted from the salary of workers towards employees provident fund is

A. Credited into reserves of company

B. Deposited in nationalised bank

C. Deposited in post office

D. Deposited in the account of worker with Provident Fund Commissioner

What is the correct answer?

4

Which of the following layouts is suited to job production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

The chart which gives an estimate about the amount of materials handling between various work stations is known as

A. Flow chart

B. Process chart

C. Travel chart

D. Operation chart

What is the correct answer?

4

Gantt chart is used for

A. Inventory control

B. Material handling

C. Production schedule

D. Machine repair schedules

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage

What is the correct answer?

4

The interchangeability can be achieved by

A. Standardisation

B. Better process planning

C. Bonus plan

D. Better product planning

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

What is the correct answer?

4

Which of the following charts are used for plant layout design?

A. Operation process chart

B. Man machine chart

C. Travel chart

D. All of these

What is the correct answer?

4

Travel charts are used to

A. Analyse material handling

B. Determine inventory control difficulties

C. Plan material handling procedure and routes

D. All of the above

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

What is the correct answer?

4

A milestone chart

A. Shows the inter dependences of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of the above

What is the correct answer?

4

The appellate authority for an industrial dispute is

A. Management

B. Labour court

C. High court/supreme court

D. Board of directors

What is the correct answer?

4

The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store

A. Inflated system

B. Primary cost method

C. Current value method

D. Fixed price method

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

What is the correct answer?

4

The allowed time for a job equals standard time plus

A. Policy allowance

B. Interference allowance

C. Process allowance

D. Learning allowance

What is the correct answer?

4

Standard time is defined as

A. Normal time + allowances

B. Normal time + idle time + allowances

C. Normal time + idle time

D. Only normal time for an operation

What is the correct answer?

4

In order to avoid excessive multiplication of facilities, the layout preferred is

A. Product layout

B. Process layout

C. Group layout

D. Static layout

What is the correct answer?

4

In steel plant the most important system for materials handling is

A. Conveyors

B. Cranes and hoists

C. Trucks

D. Locos

What is the correct answer?

4

Military type of organisation is known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

Probabilistic time for completion of any activity can be found out from

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these