Home
Current Affairs January 2024

What is the correct answer?

4

The main advantage of line organisation is its

A. Effective command and control

B. Defined responsibilities at all levels

C. Rigid discipline in the organisation

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

In the Halsey system of wage incentive plan, a worker is

A. Paid as per efficiency

B. Ensured of minimum wages

C. Not paid any bonus till his efficiency

D. Never a loser

What is the correct answer?

4

The average time recorded by work study man for an operation is called

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

String diagram is used

A. For checking the relative values of various layouts

B. When a group of workers are working at a place

C. Where processes require the operator to be moved from one place to another

D. All of the above

What is the correct answer?

4

In which of the following layouts, the lines need to the balanced

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

According to Muther, the basic principle of best layout is

A. Principle of overall integration

B. Principle of flow

C. Principle of flexibility

D. All of these

What is the correct answer?

4

Work sampling observations are taken on the basis of

A. Detailed calculations

B. Convenience

C. Table of random numbers

D. Past experience

What is the correct answer?

4

Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

What is the correct answer?

4

Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

The disadvantage of product layout is

A. High initial investment for the specialized facilities

B. Skilled labour to operate machines

C. Production time is longer, requiring more goods in inventory

D. High cost of inspection

What is the correct answer?

4

The critical path of a network represents

A. The minimum time required for completion of project

B. The maximum time required for completion of project

C. Maximum cost required for completion of project

D. Minimum cost required for completion of project

What is the correct answer?

4

The probability distribution of project completion in PERT follows following distribution

A. Normal

B. Binomial

C. Exponential

D. Gaussian

What is the correct answer?

4

Time study is

A. The appraisal, in terms of time, of the value of work involving human effort

B. Machine setting time

C. Time taken by workers to do a job

D. Method of fixing time for workers

What is the correct answer?

4

Which of the following organisation is preferred in automobile industry?

A. Functional organisation

B. Line organisation

C. Staff organisation

D. Line and staff organisations

What is the correct answer?

4

Work study is concerned with

A. Improving present method and finding standard time

B. Motivation of workers

C. Improving production capability

D. Improving production planning and control

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

Which one of the following techniques is used for determining allowances in time study?

A. Acceptance sampling

B. Linear regression

C. Performance rating

D. Work sampling

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage

What is the correct answer?

4

The important file in making a PERT is

A. An event can't be accomplished until activities leading to it are completed

B. No activity from any event can be started from preceding event till it is completed

C. Length of arrow has nothing to do with time

D. All of the above

What is the correct answer?

4

Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant

A. Sinking fund method

B. Straight line method

C. ABC charging method

D. Annuity charging method

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

What is the correct answer?

4

Motion study involves analysis of

A. Actions of operator

B. Layout of work place

C. Tooling and equipment

D. All of the above

What is the correct answer?

4

PERT is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

PERT is

A. An analytic tool in concept

B. Limit up of event oriented diagrams

C. Used for research and development projects

D. All of the above

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

Choose the wrong statement Time study is used to

A. Determine overhead expenses

B. Provide a basis for setting piece prices or incentive wages

C. Determine standard costs

D. Determine the capability of an operator to handle the number of machines

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Standard time is defined as

A. Normal time + allowances

B. Normal time + idle time + allowances

C. Normal time + idle time

D. Only normal time for an operation

What is the correct answer?

4

In fixed position layout

A. Total production cost is less

B. Material movement is less

C. Capital investment is minimum

D. All of these