Home
Current Affairs January 2024

What is the correct answer?

4

An optimum project schedule implies

A. Optimum utilization of men, machines and materials

B. Lowest possible cost and shortest possible time for project

C. Timely execution of project

D. To produce best results under given constraints

Correct Answer :

B. Lowest possible cost and shortest possible time for project


Related Questions

What is the correct answer?

4

In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

A. A standard rating system

B. A merit rating system

C. A job evaluation system

D. His individual performance

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Merit Rating is the method of determining worth of

A. A job

B. An individual employee

C. A particular division in workshop

D. Machine

What is the correct answer?

4

The average time recorded by work study man for an operation is called

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

What is the correct answer?

4

In jobbing production

A. Highly skilled workers are needed

B. Unit costs are high

C. Operations are labour-intensive

D. All of these

What is the correct answer?

4

The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)

A. (to + tp + tn)/3

B. (to + 2tp + tn)/4

C. (to + 4tp + tn)/5

D. (to + tp + 4tn)/6

What is the correct answer?

4

Standard time is defined as

A. Normal time + allowances

B. Normal time + idle time + allowances

C. Normal time + idle time

D. Only normal time for an operation

What is the correct answer?

4

The objective of time study is to determine the time required to complete a job by

A. Fast worker

B. Average worker

C. Slow worker

D. New entrant

What is the correct answer?

4

CPM has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

In time study, the rating factor is applied to determine

A. Standard time of a job

B. Merit rating of the worker

C. Fixation of incentive rate

D. Normal time of a worker

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

The determination of standard time in a complex job system is best done through

A. Stop watch time study

B. Analysis of micro-motions

C. Grouping timing technique

D. Analysis of standard data system

What is the correct answer?

4

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specification

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All of the above

What is the correct answer?

4

A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the

A. Fixed cost line

B. Variable cost line

C. Total cost line

D. Sales revenue line

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Time study is carried out

A. By finding all the significant informations regarding the job, work place and machine tool etc.

B. By breaking up each operation into small elements which are measurable with the help of the measuring device accurately

C. By observing and recording the time taken by the operator for an operation

D. All of the above

What is the correct answer?

4

In Halsey 50-50 plan, output standards are established

A. By time study

B. From previous production records

C. From one's judgement

D. All of the above

What is the correct answer?

4

Time study is

A. The appraisal, in terms of time, of the value of work involving human effort

B. Machine setting time

C. Time taken by workers to do a job

D. Method of fixing time for workers

What is the correct answer?

4

Pick up the incorrect statement from the following

A. An activity of the project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn (to scale from) left to right

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

In breakeven analysis, total cost consists of

A. Fixed cost

B. Variable cost

C. Fixed cost + variable cost

D. Fixed cost + variable cost + overheads

What is the correct answer?

4

Job enrichment technique is applied to

A. Reduce labour monotony

B. Overcome boring and de-motivating work

C. Make people happy

D. All of the above

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

Indirect expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. All of these