Home
Current Affairs January 2024

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

Correct Answer :

D. Reducing inventory costs


Related Questions

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

Which of the following conditions are necessary for applying linear programming?

A. These must be a well defined objective function.

B. The decision variables should be interrelated and nonnegative.

C. The resources must be in limited supply.

D. All of the above

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

PMTP (predetermined motion time systems) include

A. MTM (method time measurement)

B. WFS (work factor systems)

C. BNTS (basic motion time study)

D. All of the above

What is the correct answer?

4

The disadvantage of product layout is

A. High initial investment for the specialized facilities

B. Skilled labour to operate machines

C. Production time is longer, requiring more goods in inventory

D. High cost of inspection

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

Product layout is used for

A. Job production

B. Batch production

C. Mass production

D. Any one of these

What is the correct answer?

4

Which of the following statement is wrong?

A. An activity consumes time and resources whereas an event does not consume time or resources.

B. The performance of a specific task is called an activity.

C. An event is an instantaneous point in time at which an activity begins or ends.

D. The turning of a job on lathe is an event whereas job turned is an activity.

What is the correct answer?

4

Work sampling is applied for

A. Estimation of the percentage utilisation of machine tools

B. Estimating the percentage of the time consumed by various job activities

C. Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible

D. All of the above

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

Material handling in automobile industry is done by

A. Overhead crane

B. Trolley

C. Belt conveyor

D. All of the above

What is the correct answer?

4

Actual performance of a task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

Product layout is best suited where

A. One type of product is produced

B. Product is standardised

C. Product is manufactured in large quantities

D. All of the above

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

What is the correct answer?

4

Abbreviated work factor data is applied for

A. Material handling operation

B. Maintenance operation

C. Packing and shipping operation

D. All of these

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

What is the correct answer?

4

Material handling and plant location is analysed by

A. Gantt chart

B. Bin chart

C. Emerson chart

D. Travel chart

What is the correct answer?

4

For material transportation, conveyors are used when the prevailing conditions include

A. Loads are uniform

B. Routes do not vary

C. Materials move relatively continuously

D. All of these

What is the correct answer?

4

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it

A. Consumes time, but no resources

B. Consumes resources but no time

C. Consumes neither time nor resources

D. Is a dangling event

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

What is the correct answer?

4

The first method invented for planning projects was

A. Bar chart method

B. Milestone chart

C. Critical path method (CPM)

D. Programme evaluation and review technique (PERT)

What is the correct answer?

4

In fixed position layout

A. Total production cost is less

B. Material movement is less

C. Capital investment is minimum

D. All of these

What is the correct answer?

4

Indirect expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. All of these