Home
Current Affairs January 2024

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

Correct Answer :

C. A project can be subdivided into a set of predictable, independent activities


Related Questions

What is the correct answer?

4

Simplex method is the method used for

A. Value analysis

B. Network analysis

C. Linear programming

D. Queuing theory

What is the correct answer?

4

Break-even analysis consists of

A. Fixed expenses

B. Variable cost

C. Sales revenue

D. All of these

What is the correct answer?

4

Micro motion study is

A. Analysis of a man-work method by using a motion picture camera with a timing device in the field of view

B. Motion study observed on enhanced time intervals

C. Motion study of a sequence of operations conducted systematically

D. Study of man and machine conducted simultaneously

What is the correct answer?

4

The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

What is the correct answer?

4

The routing function in a production system design is concerned with

A. Manpower utilisation

B. Quality assurance of the product

C. Machine utilisation

D. Optimising material flow through the plant

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines

What is the correct answer?

4

The disadvantage of product layout is

A. High initial investment for the specialized facilities

B. Skilled labour to operate machines

C. Production time is longer, requiring more goods in inventory

D. High cost of inspection

What is the correct answer?

4

A-B-C analysis is used in

A. CPM

B. PERT

C. Inventory control

D. All of these

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

The main advantage of line organisation is its

A. Effective command and control

B. Defined responsibilities at all levels

C. Rigid discipline in the organisation

D. All of the above

What is the correct answer?

4

The term 'value' in value engineering refers to

A. Total cost of the product

B. Selling price of the product

C. Utility of the product

D. Manufactured cost of the product

What is the correct answer?

4

Work study comprises following main techniques

A. Method study and work measurement

B. Method study and time study

C. Time study and work measurement

D. Method study and job evaluation

What is the correct answer?

4

In PERT analysis, critical path is obtained by joining events having

A. +ve slack

B. -ve slack

C. Zero slack

D. Dummy activities

What is the correct answer?

4

Pick up the correct statement from the following

A. Critical path method is an improvement upon bar chart method

B. Critical path method provides a realistic approach to the daily problems

C. Critical path method avoids delays which are very common in bar chart

D. All of the above

What is the correct answer?

4

Breakeven point is the point where

A. Fixed and variable cost lines intersect

B. Fixed and total cost lines intersect

C. Variable and total cost lines intersect

D. Sales revenue and total expensive lines intersect

What is the correct answer?

4

PERT is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

A graphical device used to determine the breakeven point and profit potential under varying conditions of output and costs, is known as

A. Gantt chart

B. Flow chart

C. Breakeven chart

D. PERT chart

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

In inventory control, the economic order quantity is the

A. Optimum lot size

B. Highest level of inventory

C. Lot corresponding to breakeven point

D. Capability of a plant to produce

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

Process layout is also known as

A. Analytical-layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Which of the following layouts is suited to job production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Product layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

The deductions for, employees provident fund start

A. Immediately on joining the service

B. After 60 days of joining the service

C. After 100 days of joining the service

D. After 240 days of joining the service

What is the correct answer?

4

Military type of organisation is known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

Travel charts provide

A. An idea of the flow of materials at various stages

B. A compact estimate of the handling which must be done between various work sections

C. The information for changes required in rearranging material handling equipment

D. An approximate estimate of the handling which must be done at a particular station

What is the correct answer?

4

A big advantage of PERT over Gantt charts is that in the former case

A. Activities and events are clearly shown

B. Early start and late finish of an activity are clearly marked

C. Activity times are clear

D. Interrelationship among activities is clearly shown.

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed