A project will always be behind schedule, if left uncorrected
Cost of project will always be more than the estimated cost, if no timely corrections are taken
A project can be subdivided into a set of predictable, independent activities
Activities are fixed and can't be changed
C. A project can be subdivided into a set of predictable, independent activities
Value analysis
Network analysis
Linear programming
Queuing theory
Fixed expenses
Variable cost
Sales revenue
All of these
Analysis of a man-work method by using a motion picture camera with a timing device in the field of view
Motion study observed on enhanced time intervals
Motion study of a sequence of operations conducted systematically
Study of man and machine conducted simultaneously
Ordering procedure
Forecasting sales
Production planning
Despatching and expediting
Manpower utilisation
Quality assurance of the product
Machine utilisation
Optimising material flow through the plant
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with starting of processes
Regulates the progress of job through various processes
When work should start and how much work should be completed during a certain period
When work should complete
That how idle time can be minimized
Proper utilisation of machines
High initial investment for the specialized facilities
Skilled labour to operate machines
Production time is longer, requiring more goods in inventory
High cost of inspection
CPM
PERT
Inventory control
All of these
Rowan Plan
Taylor Differential Piece rate system
Halsey Premium plan
Day work plan
Effective command and control
Defined responsibilities at all levels
Rigid discipline in the organisation
All of the above
Total cost of the product
Selling price of the product
Utility of the product
Manufactured cost of the product
Method study and work measurement
Method study and time study
Time study and work measurement
Method study and job evaluation
+ve slack
-ve slack
Zero slack
Dummy activities
Critical path method is an improvement upon bar chart method
Critical path method provides a realistic approach to the daily problems
Critical path method avoids delays which are very common in bar chart
All of the above
Fixed and variable cost lines intersect
Fixed and total cost lines intersect
Variable and total cost lines intersect
Sales revenue and total expensive lines intersect
Time oriented technique
Event oriented technique
Activity oriented technique
Target oriented technique
Gantt chart
Flow chart
Breakeven chart
PERT chart
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with starting of processes
Regulates the progress of job through various processes
Top level executives have to do excessive work
Structure is rigid
Communication delays occur
All of the above
Optimum lot size
Highest level of inventory
Lot corresponding to breakeven point
Capability of a plant to produce
PERT deals with events and CPM with activities
Critical path is determined in PERT only
Costs are considered on CPM only and not in PERT
Guessed times are used in PERT and evaluated times in CPM
Analytical-layout
Synthetic layout
Static product layout
None of these
Process layout
Product layout
Fixed position layout
Plant layout
Analytical layout
Synthetic layout
Static product layout
None of these
Immediately on joining the service
After 60 days of joining the service
After 100 days of joining the service
After 240 days of joining the service
Line organisation
Functional organisation
Line and staff organisation
Line, staff and functional organisation
An idea of the flow of materials at various stages
A compact estimate of the handling which must be done between various work sections
The information for changes required in rearranging material handling equipment
An approximate estimate of the handling which must be done at a particular station
Activities and events are clearly shown
Early start and late finish of an activity are clearly marked
Activity times are clear
Interrelationship among activities is clearly shown.
A project will always be behind schedule, if left uncorrected
Cost of project will always be more than the estimated cost, if no timely corrections are taken
A project can be subdivided into a set of predictable, independent activities
Activities are fixed and can't be changed