Home

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

Please do not use chat terms. Example: avoid using "grt" instead of "great".

You can do it
  1. The critical path of a network represents
  2. Works cost implies
  3. If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual…
  4. For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs.…
  5. Which of the following statement is correct?
  6. PERT analysis is based on
  7. According to Muther, the basic principle of best layout is
  8. PERT requires
  9. Gantt chart is used for
  10. The wastage of material in the store is taken into account by the following method in the evaluation…
  11. Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
  12. Which one of the following techniques is used for determining allowances in time study?
  13. String diagram is used
  14. For a product layout the material handling equipment must
  15. String diagram is used when
  16. A critical activity has
  17. In process layout
  18. 'Value' for value engineering and analysis purposes is defined as
  19. Which of the following organisations is best suited for steel plants
  20. Critical path on PERT/CPM chart is obtained by joining the events having
  21. The time by which the activity completion time can be delayed without affecting the start of succeeding…
  22. The most suitable incentive plan for the maintenance section of an industry will be
  23. Pick up the correct step used for scheduling a project by C.P.M.
  24. Process layout is employed for
  25. An activity of the project is graphically represented by ________ on the network diagram.
  26. The first method invented for planning projects was
  27. Which of the following statement is correct?
  28. If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start…
  29. Military organisation is known as
  30. In steel plant the most important system for materials handling is