Home
Current Affairs January 2024

What is the correct answer?

4

Pick up the correct statement from the following

A. Critical path method is an improvement upon bar chart method

B. Critical path method provides a realistic approach to the daily problems

C. Critical path method avoids delays which are very common in bar chart

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

Product layout is used for

A. Job production

B. Batch production

C. Mass production

D. Any one of these

What is the correct answer?

4

Which of the following statement is wrong?

A. An activity consumes time and resources whereas an event does not consume time or resources.

B. The performance of a specific task is called an activity.

C. An event is an instantaneous point in time at which an activity begins or ends.

D. The turning of a job on lathe is an event whereas job turned is an activity.

What is the correct answer?

4

Performance rating is equal to

A. Observed performance + normal performance

B. Observed performance - normal performance

C. Observed performance × normal performance

D. None of the above

What is the correct answer?

4

The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)

A. (to + tp + tn)/3

B. (to + 2tp + tn)/4

C. (to + 4tp + tn)/5

D. (to + tp + 4tn)/6

What is the correct answer?

4

Probabilistic time for completion of any activity can be found out from

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

The process capability of a machine is defined as the capability of the machine to

A. Produces a definite volume of work per minute

B. Perform definite number of operations

C. Produce job at a definite spectrum of speed

D. Holds a definite spectrum of tolerance and surface finish

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

Graphical method, simplex method, and transportation method are concerned with

A. Breakeven analysis

B. Value analysis

C. Linear programming

D. Queueing theory

What is the correct answer?

4

Value engineering aims at finding out the

A. Depreciation value of a product

B. Resale value of a product

C. Major function of the item and accomplishing the same at least cost without change in quality

D. Breakeven point when machine requires change

What is the correct answer?

4

For ship vessel industry the following layout is best suited

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

A. A standard rating system

B. A merit rating system

C. A job evaluation system

D. His individual performance

What is the correct answer?

4

Works cost implies

A. Primary cost

B. Factory cost

C. Factory expenses

D. Primary cost + factory expenses

What is the correct answer?

4

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

The reasons which are basically responsible for the formation of a queue should be that

A. The average service rate Hess than the average arrival rate

B. Output rate is linearly proportional to input

C. Output rate is constant and the input varies in a random manner

D. All of the above

What is the correct answer?

4

A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialisation of operation

What is the correct answer?

4

The allowed time for a job equals standard time plus

A. Policy allowance

B. Interference allowance

C. Process allowance

D. Learning allowance

What is the correct answer?

4

CPM stands for

A. Combined Process Method

B. Critical Path Method

C. Common Planning Method

D. Critical Process Method

What is the correct answer?

4

The most suitable incentive plan for the maintenance section of an industry will be

A. Piece rate system

B. Group incentive plan

C. Profit sharing plans

D. Simplification

What is the correct answer?

4

According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse minimum DAM = Defender's Adverse minimum)

A. CAM < DAM

B. CAM > DAM

C. CAM = DAM

D. There is no such criterion

What is the correct answer?

4

In inventory control, the economic order quantity is the

A. Optimum lot size

B. Highest level of inventory

C. Lot corresponding to breakeven point

D. Capability of a plant to produce

What is the correct answer?

4

The grouping of activities into organisational units is called

A. Corporate plans

B. Higher level management

C. Functional authority

D. Departmentation

What is the correct answer?

4

Bar chart is suitable for

A. Large project

B. Major work

C. Minor work

D. All of these

What is the correct answer?

4

In the Halsey system of wage incentive plan, a worker is

A. Paid as per efficiency

B. Ensured of minimum wages

C. Not paid any bonus till his efficiency

D. Never a loser

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

Break-even analysis can be used for

A. Short run analysis

B. Long run analysis

C. Average of above two run analysis

D. There is no such criterion

What is the correct answer?

4

Which of the following layouts is suited for mass production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

The standard time for a job is

A. Total work content

B. Base time + relaxation time

C. Total work content + basic time

D. Total work content + delay contingency allowance

What is the correct answer?

4

The probability distribution of activity times in PERT follows following distribution

A. Normal

B. Binomial

C. Beta

D. Exponential

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. CPS (Critical Path Scheduling)

D. All of the above

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines