Home
Current Affairs January 2024

What is the correct answer?

4

Gantt chart gives information about

A. Scheduling and routing

B. Sales

C. Production schedule

D. Machine utilisation

Correct Answer :

C. Production schedule


Related Questions

What is the correct answer?

4

Pick up the correct statement from the following

A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed

B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project

D. All of the above

What is the correct answer?

4

The most important function of inventory control is

A. Stock control system

B. To run the stores effectively

C. Technical responsibility for the state of materials

D. All of the above

What is the correct answer?

4

Work study is concerned with

A. Improving present method and finding standard time

B. Motivation of workers

C. Improving production capability

D. Improving production planning and control

What is the correct answer?

4

Queueing theory deals with problems of

A. Material handling

B. Reducing the waiting time or idle time

C. Better utilization of man services

D. Effective use of machines

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

In breakeven analysis, total cost consists of

A. Fixed cost

B. Variable cost

C. Fixed cost + variable cost

D. Fixed cost + variable cost + overheads

What is the correct answer?

4

Material handling in automobile industry is done by

A. Overhead crane

B. Trolley

C. Belt conveyor

D. All of the above

What is the correct answer?

4

Micro motion study is

A. Analysis of a man-work method by using a motion picture camera with a timing device in the field of view

B. Motion study observed on enhanced time intervals

C. Motion study of a sequence of operations conducted systematically

D. Study of man and machine conducted simultaneously

What is the correct answer?

4

A diagram showing the path followed by men and materials while performing a task is known as

A. String diagram

B. Flow process chart

C. Travel chart

D. Flow diagram

What is the correct answer?

4

Graphical method, simplex method, and transportation method are concerned with

A. Breakeven analysis

B. Value analysis

C. Linear programming

D. Queueing theory

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All of the above

What is the correct answer?

4

In perpetual inventory control, the material is checked as it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Middle value

What is the correct answer?

4

One of the basic essentials of an incentive plan is that

A. A differential piece rate system should exist

B. Minimum wages should be guaranteed

C. Provide incentive to group efficiency performance

D. All standards should be based on time studies

What is the correct answer?

4

Performance rating is equal to

A. Observed performance + normal performance

B. Observed performance - normal performance

C. Observed performance × normal performance

D. None of the above

What is the correct answer?

4

Job evaluation is the method of determining the

A. Relative worth of jobs

B. Skills required by a worker

C. Contribution of a worker

D. Contribution of a job

What is the correct answer?

4

Which of the following are the principles of material handling?

A. Keep all the handling to the minimum

B. Select only efficient handling equipment

C. Move the heaviest weight to the least distance

D. All of the above

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

What is the correct answer?

4

The production cost per unit can be reduced by

A. Producing more with increased inputs

B. Producing more with the same inputs

C. Eliminating idle time

D. Minimising resource waste

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines

What is the correct answer?

4

The appellate authority for an industrial dispute is

A. Management

B. Labour court

C. High court/supreme court

D. Board of directors

What is the correct answer?

4

The determination of standard time in a complex job system is best done through

A. Stop watch time study

B. Analysis of micro-motions

C. Grouping timing technique

D. Analysis of standard data system

What is the correct answer?

4

Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

What is the correct answer?

4

M.T.M. is used to

A. Improve existing methods

B. Establish time standards

C. Develop effective methods in advance of the beginning of production

D. All of the above

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

Military type of organisation is known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

Standard time is defined as

A. Normal time + allowances

B. Normal time + idle time + allowances

C. Normal time + idle time

D. Only normal time for an operation